Filling in the Forms
We started filling in the forms today, leveling the ground up to prepare for the slab going in, hopefully next week. Before that happens we have to put in the rough plumbing, insulation and the piping for the radiant in-floor heating.
We also spent a good part of the day pulling nails from our form bracing so that we could reuse the wood as bracing for the timber-frame and the plywood to build forms for our tower anchors.
That’s Eric driving the backhoe, Bob driving the compactor, and Ian pulling nails. Not unusually Gator found a way to get very very dirty.