Getting closer

We didn’t get a whole lot done on the structure this weekend but there was lots of work none-the-less. We had a meeting with Paul and Mike Saturday morning and discussed various aspects of the structure as it stands now and going forward. It should be noted that Paul and Mike have remained remarkably congenial over the course of this endeavour, any disagreements have been smoothed over quickly, and neither has lost sight that the end goal is to get our house built. For those who don’t know disagreements, and even outright warfare between builders and architects is, while not exactly legend, certainly very well documented in the annals of home building.

We met with Pete Mack in the afternoon, he’s going to be our contractor for the straw bale portion. We chatted with him for nearly three hours, he’s a great guy and we’re looking forward to the raising. The raising will now be on the weekend of November 9th. I have every confidence that we will be able to make this deadline.

The post and beam should be done this week, there’s only five short posts and one beam to go. We have to get some more custom boots made, so they can’t raise the rest until we have those. Until then Jerry and his guys will be working on the trusses.

There’s about a million little details that have to be in place before straw bale can go up, we have to take care of all of those over the next couple of weeks.

We took some pictures of the house with almost all of the posts and beams in place. The front sure looks tall.